116 entries

A

AACE 11R-88 (EVMS)

AACE International's Recommended Practice on Required Skills and Knowledge of an Earned Value Management System — the reference for what an EVMS implementation should contain.

AACE 18R-97 (Cost Estimate Classification System)

AACE Recommended Practice defining a five-class cost estimate classification system based on level of project definition, end usage, methodology and expected accuracy range. The most widely cited estimate classification standard across UK and international capital projects.

AACE 57R-09 (Integrated Cost and Schedule Risk Analysis)

AACE International Recommended Practice for integrated cost-schedule risk analysis using the Risk Driver method — discrete risks that simultaneously affect multiple activities, modelled via Monte Carlo simulation of the CPM network.

AACE 113R-20 (Integrated Cost and Schedule Risk Analysis — Parametric and Expected Value)

AACE Recommended Practice for integrated cost-schedule risk analysis using combined parametric cost estimating with expected-value risk treatment. An alternative to 57R-09's Risk Driver method, preferred where parametric cost data is the primary input.

AACE International

The Association for the Advancement of Cost Engineering — the global professional body whose Recommended Practices are the reference standard for project controls, cost engineering and risk analysis.

AMP (Asset Management Period)

The five-year regulatory cycle within which UK water companies plan, fund and deliver capital investment, governed by Ofwat's price review process.

As-Built Schedule

A retrospective schedule showing what actually happened on a project — the real start and finish dates of every activity — used primarily for delay analysis and dispute evidence.

As-Planned Schedule

The schedule showing what the project intended to do at a specific reference point — typically the baseline at contract signature, used as the starting point for delay analysis.

B

C

CADMID

The UK MoD's six-phase acquisition lifecycle. For project controls practitioners — what each phase demands: QRA at Concept, EVMS at Manufacture, through-life cost tracking In-Service.

CADMID Lifecycle

How CADMID's six phases shape the controls function — QRA and cost confidence at Concept, full EVMS at Manufacture, through-life cost tracking In-Service. Gateway tests and failure modes at each transition.

CDM Regulations 2015

The Construction (Design and Management) Regulations 2015 — UK statutory health and safety framework allocating design and management duties to Clients, Principal Designers, Principal Contractors and duty holders on construction projects.

Concurrent Delay

The situation where two or more delay events — one caused by the Employer and one caused by the Contractor — affect the same period of project time, creating a disputed entitlement to time and cost.

Contingency vs Management Reserve

Contingency covers known unknowns inside the project budget; management reserve covers unknown unknowns above it. A practitioner guide to the difference, who controls each, how drawdown works, and why conflating them obscures real performance.

Control Account

A management control point in an EVM system where scope, schedule, and budget are integrated and performance is measured.

Correlation in QRA

The statistical relationship between risks or activity durations in a quantitative risk model — ignoring correlation typically underestimates total project risk.

Cost Breakdown Structure (CBS)

A hierarchical breakdown of all project costs, organised by cost type or element rather than by deliverable — the cost-focused counterpart to the WBS.

Cost Performance Index (CPI)

An EVM metric that measures cost efficiency: CPI = Earned Value ÷ Actual Cost. Below 1.0 means the project is spending more than the work is worth.

Cost Risk Analysis (CRA)

A probabilistic assessment of project cost that models uncertainty in estimates and discrete cost risks to produce a range of possible outturn costs.

Critical Path Length Index (CPLI)

A forward-looking DCMA schedule metric that compares the time available to the time needed to complete the project — below 0.95 signals schedule pressure.

Critical Path Method (CPM)

A scheduling technique that identifies the longest sequence of dependent activities through a project — the path that determines the earliest possible finish date.

Critical Path vs Critical Chain

Critical Path Method (CPM) sequences activities by logic dependencies. Critical Chain Project Management (CCPM) extends CPM by also constraining for resource dependencies, treating shared resources as the binding factor.

Criticality Index

The percentage of Monte Carlo iterations in which an activity lies on the critical path. A probabilistic measure of how often an activity actually drives project completion, used in QSRA / risk-loaded schedule analysis.

D

E

Earned Schedule (ES)

A time-based extension of EVM that addresses the limitations of Schedule Variance and SPI once a project passes its planned completion date — giving a more reliable schedule performance measure late in delivery.

Earned Value (EV) vs Planned Value (PV)

EV is the budgeted value of work actually completed; PV is the budgeted value of work that was planned to be complete by now — the gap between them measures schedule performance.

Earned Value Management (EVM)

A performance measurement technique that integrates scope, schedule, and cost to give an objective picture of where a project really stands.

Earned Value vs Earned Schedule

Earned Value (EV) measures schedule performance in cost units and converges to zero at project end. Earned Schedule (ES) measures schedule performance in time units and stays meaningful through the entire project lifecycle.

Estimate at Completion (EAC)

A forecast of the total expected cost of the project based on actual performance to date and any revised estimate for remaining work.

Estimate to Complete (ETC)

The expected cost to complete all remaining project work from the current data date to the end.

Expected Monetary Value (EMV)

The probability-weighted average cost or benefit of a risk event, calculated by multiplying the probability of occurrence by the financial impact.

Extension of Time (EOT)

A contractual mechanism by which the Contractor's completion date is extended to reflect delays caused by Employer-risk events — protecting the Contractor from liquidated damages for excusable delay.

F

H

I

L

M

N

National Audit Office (NAO)

The UK's independent public-spending watchdog — auditing how government departments and major programmes deliver value for money and reporting findings to Parliament.

Near-Critical Path

A path through the project network with low (but non-zero) total float — close enough to critical that any slip on it can promote it to the critical path. DCMA 14-point assessment monitors activities with ≤7 working days of float as near-critical.

NEC4 Accepted Programme

The current, contractually recognised programme under an NEC4 contract — the reference against which progress, compensation events and extensions of time are assessed.

NEC4 Clause 31 (Programme Submission)

The NEC4 clause that requires the Contractor to submit a programme for acceptance — defining what the programme must contain and how the Project Manager responds.

NEC4 Clause 32 (Revising the Programme)

The NEC4 clause that requires the Contractor to revise the Accepted Programme at defined intervals — keeping the contractual reference programme current throughout delivery.

NEC4 Compensation Event

Under NEC4, a defined event that entitles the Contractor to additional time, cost or both — assessed against the Accepted Programme in a structured, contemporaneous process.

NEC4 Early Warning

A contractual obligation under NEC4 to notify the other party of any matter that could affect price, completion, Key Dates or performance — designed to surface problems while they can still be managed.

NEC4 Key Date

A contractually-binding interim milestone under NEC4 — a point at which the Contractor must complete specific Condition for the Project Manager to be able to proceed with the next activity.

NEC4 Sectional Completion

A mechanism under NEC4 that allows the works to be handed over in defined Sections, each with its own Completion Date and associated rights and obligations, rather than as a single completion event.

NEC4 Target Cost (Option C)

An NEC4 pricing option where the Contractor is paid actual cost plus Fee, with a target cost agreed up front and gain or pain shared between the parties based on the final outturn.

O

P

Q

R

Residual Risk

The risk exposure that remains after mitigation actions have been applied — the risk the project carries even after doing everything reasonable to reduce it.

Resource Breakdown Structure (RBS)

A hierarchical breakdown of all project resources — people, plant, and materials — organised by type, used for resource planning and cost allocation.

Resource Levelling vs Resource Smoothing

Resource levelling adjusts the schedule to stay within resource limits, potentially extending the project; resource smoothing adjusts resource use without extending the project end date.

Responsibility Assignment Matrix (RAM)

A matrix that crosses the WBS with the OBS to identify who is responsible for each piece of work — the formal basis for control account ownership in EVM.

RIBA Plan of Work

The Royal Institute of British Architects' standard framework for the UK construction project lifecycle — defining eight stages from strategic definition through to in-use, each with its own outputs and gateway criteria.

Risk Appetite Statement

A formal declaration by an organisation of the amount and type of risk it is prepared to accept in pursuit of its objectives.

Risk Appetite vs Risk Tolerance

Risk appetite is how much risk an organisation is willing to seek out; risk tolerance is the maximum level of risk it can absorb before it must act.

Risk Breakdown Structure (RBS)

A hierarchical classification of project risks by source or category, used to organise the risk register and identify gaps in risk identification.

Risk Mitigation Plan

A documented set of actions designed to reduce the probability or impact of a specific risk — linked to the risk register, owned by an accountable individual, and tracked for completion.

Risk Owner

The named individual accountable for managing a specific risk — responsible for monitoring it, implementing mitigation actions, and reporting status through the risk governance cycle.

Risk Register

A structured log of identified project risks, recording what could go wrong, how likely it is, what the impact would be, and what is being done about it.

Rolling Wave Planning

A progressive-elaboration planning technique where near-term work is planned in detail and later work is kept at summary level until scope becomes clearer.

S

S-Curve

A cumulative cost or progress curve that typically forms an S-shape over the project lifecycle, starting slowly, accelerating through execution, then tapering at handover.

Safran Risk

An enterprise-grade schedule and cost risk analysis tool widely used on UK defence, nuclear and infrastructure programmes for Monte Carlo QRA against integrated Primavera P6 or Microsoft Project schedules.

Schedule Performance Index (SPI)

An EVM metric that measures schedule efficiency: SPI = Earned Value ÷ Planned Value. Below 1.0 means the project is behind plan.

Schedule Quality Metrics

The broader discipline of assessing whether a programme schedule is fit to be relied upon — covering structural integrity, resource feasibility, baseline drift, probabilistic readiness and earned-value compatibility. DCMA 14 is the best-known framework, but only one entry point.

Schedule Risk Analysis (SRA)

A probabilistic analysis that models uncertainty in activity durations and discrete schedule risks to produce a range of possible project completion dates.

SCL Delay and Disruption Protocol

The Society of Construction Law's guidance on managing and analysing delay and disruption claims on construction contracts — widely referenced in UK courts, adjudication and expert reports.

Secondary Risk

A new risk that arises as a direct result of implementing a risk response — a side-effect of the mitigation itself.

Sensitivity Analysis (Tornado Chart)

An analysis that identifies which risks or uncertainties have the greatest influence on project cost or schedule outcomes — typically displayed as a ranked bar chart.

Soft Constraint (Preferred Constraint)

A scheduling preference rather than a mandatory date — the tool will try to honour it but will not override the network logic if the calculated date conflicts.

Start-to-Finish (SF) Logic

The rarest dependency type: the successor activity cannot finish until the predecessor has started — almost always a sign of poor schedule modelling.

Start-to-Start (SS) Logic

A dependency type where the successor activity cannot start until the predecessor has started — useful for modelling overlapping or concurrent work.

T

V

W

Need something explained?

If there's a project controls term you'd like us to cover, or you want to talk through how these techniques apply to your programme, get in touch.