Glossary
AACE 11R-88 (Required Skills and Knowledge of Cost Engineering)
AACE International's Recommended Practice setting out the skills and knowledge expected of a cost engineer. It is not an earned value standard - EVMS requirements sit in ANSI/EIA-748.
AACE Recommended Practice 11R-88 is titled Required Skills and Knowledge of Cost Engineering. It describes the skills and knowledge a cost engineer is expected to hold across estimating, cost control, planning and scheduling, and risk management. It is a competence reference. It is not a method for building or auditing an earned value system.
11R-88 is sometimes cited as an EVMS standard. It is not one. The 32 EVMS guidelines belong to ANSI/EIA-748 (current revision). International guidance sits in ISO 21508:2018, Earned value management in project and programme management, and the APM Earned Value Management Handbook is the usual UK practitioner reference.
A controls team describing its EVMS should use ANSI/EIA-748 terms: control account plans aligned to the Performance Measurement Baseline, monthly variance analysis at control account manager level, and formal baseline change control. The PMB comprises control accounts, summary-level planning packages and undistributed budget; management reserve sits outside it. Cite 11R-88 only when discussing the skills and competence of the people doing the work.
Used in practice
Need this on a live programme?
SOMA delivers this on live UK programmes — and trains teams in it. Where it fits:
Putting these techniques into practice?
SOMA provides independent project controls consultancy for UK programmes. We can help you apply QRA, EVM, schedule risk analysis, and more.