Maintained by Adam O’NeillDirector, QRA SpecialistLast reviewed

Earned Value (classical) vs Earned Schedule — schedule metrics compared.

Earned Value (EV)Earned Schedule (ES)
Unit of measureCost (£, $)Time (days, weeks, months)
Headline schedule metricsSV = EV − PV; SPI = EV ÷ PVSV(t) = ES − AT; SPI(t) = ES ÷ AT
Behaviour at project endConverges to 0 / 1.0 even on late projects (the convergence problem)Stays meaningful — reflects actual schedule performance through closeout
Best forMid-project cost-schedule integration; baseline-vs-actual cost performanceSchedule forecasting late in the lifecycle; honest closeout metrics
Reference frameworkANSI/EIA-748; ISO 21508:2018Lipke (2003) Earned Schedule
Tool supportAll EVMS tools natively (Deltek, Cobra, Acumen, Ecosys)Same tools — usually a configurable report; some need custom calc
Typical UK useDefault schedule metric on NEC4 and MoD EVMS contractsIncreasingly used as a supplementary metric on Major Projects under Initial/Main Gate or NISTA Gateway Review scrutiny

Earned Value Management produces two schedule metrics: Schedule Variance (SV = EV − PV) and the Schedule Performance Index (SPI = EV ÷ PV). Both express schedule performance in cost units. Earned Schedule (ES), introduced by Walt Lipke in 2003, converts schedule performance back into time by asking a different question — "at what point in the planned schedule should we have earned the value we've earned so far?" — and produces a parallel set of metrics in time units: SV(t) and SPI(t).

The reason this matters is a well-known limitation of classical EVM. SPI and SV always converge to 1.0 and 0 respectively at project completion, regardless of whether the project finished early, on time, or six months late, because EV and PV both equal BAC at completion. A project that is six months late will, in its final report, show SPI = 1.0 — a blatantly wrong reading of schedule performance. Earned Schedule's SPI(t) does not have this convergence problem; it remains a faithful measure of schedule efficiency through the closeout phase.

For UK infrastructure programmes that report monthly through the late stages of delivery, SPI(t) is the more honest metric. Most modern EVMS implementations now produce both — Earned Value figures for traditional cost-schedule integration, Earned Schedule figures for forward-looking schedule forecasting. Practitioners working on programmes where schedule completion is governance-critical (NEC4, MOD Initial or Main Gate, NISTA Gateway Reviews) should be comfortable reading and producing both sets of metrics.

Used in practice

Need this on a live programme?

SOMA delivers this on live UK programmes — and trains teams in it. Where it fits:

Frequently asked

What is the difference between Earned Value and Earned Schedule?
Earned Value Management measures schedule performance in cost units (SV = EV − PV, SPI = EV ÷ PV). Earned Schedule converts these into time units (SV(t), SPI(t)) by asking when you should have earned the value you have earned. The practical difference is that classical EV's schedule metrics converge to zero/1.0 at project completion even on late projects, while Earned Schedule's time-based metrics remain meaningful through closeout.
Why does SPI become unreliable late in a project?
SPI = EV ÷ PV. As a project approaches completion, both EV and PV approach the Budget at Completion (BAC) — eventually they're equal, and SPI = 1.0 regardless of how late the project actually finished. This means a project six months overdue can report SPI = 1.0 in its final month. Earned Schedule's SPI(t) doesn't suffer from this — it expresses schedule performance in actual time units, so a six-month overrun shows as SPI(t) ≈ 0.85 even at closeout.
Should we use Earned Value or Earned Schedule on a UK infrastructure programme?
Both. Earned Value is the contractual / EVMS-mandated framework on NEC4 and MoD contracts and remains the default for cost-schedule integration. Earned Schedule is supplementary — most useful for forward-looking schedule forecasting, especially in the back half of the programme when SPI is no longer reliable. Many modern EVMS implementations produce both; reporting both keeps the client honest.
Who developed Earned Schedule?
Walt Lipke, who introduced the framework in a 2003 paper while at Tinker Air Force Base. The methodology has since been formalised in AACE International Recommended Practice 64R-11 ("CPM Schedule Risk Modelling and Analysis") and is now standard supplementary practice on major US DoD and UK MoD programmes.

Putting these techniques into practice?

SOMA provides independent project controls consultancy for UK programmes. We can help you apply QRA, EVM, schedule risk analysis, and more.