Adam O'NeillLast updated 8 min readPart of Defence & government project controls

What is CADMID Concept phase?

Concept is the first phase of the MoD's CADMID acquisition lifecycle. The programme defines the requirement and assesses options at a high level. It ends at Initial Gate, where a Strategic Outline Case (the initial business case) supports the decision to enter Assessment. Controls deliverables are a wide-range cost estimate, option-level QRA, a reference-class check and a strategic risk register.

Concept-phase controls deliverables. The register v0.1 and the sequencing are SOMA convention, not a mandated list.

Point in ConceptControls deliverableMethod referenceWhat the reviewer checks
EarlyStrategic outline cost rangeAACE Class 5 under 17R-97 (generic); 18R-97 (process industries) and 56R-08 (building) are the nearest published applicationsThe range is wide enough for the definition of the requirement
MidOption-level QRA for each credible solutionRange estimating and parametric methods: AACE 41R-08, 42R-08; 40R-08 for contingency principlesUncertainty differs between options according to technical maturity
MidReference-class comparisonHM Treasury Green Book, optimism bias and riskEach option range has been compared with the outturn of comparable programmes
LateStrategic risk register v0.1ISO 31000; MoD risk management guidanceThe top risks are consistent with the option set and the recommended option
EndControls inputs to the Strategic Outline CaseGreen Book five case model (strategic, economic, commercial, financial, management)Every figure traces to a model, a reference dataset or a stated assumption

Where Concept fits

CADMID has six phases: Concept, Assessment, Demonstration, Manufacture, In-service and Disposal. Concept defines the requirement, identifies candidate solutions at a high level and ends at Initial Gate. The approval document at Initial Gate is a Strategic Outline Case, the initial business case under the Green Book five case model, or on some projects an Outline Business Case. Main Gate, at the end of Assessment, approves the Full Business Case.

Initial Gate is a decision to enter Assessment with a manageable option set, to pause, or to stop. Approvals are given through the Investment Approvals Committee, and the route depends on the value of the programme, the delegations in place and, for large cases, HM Treasury approval. JSP 507 sets the investment appraisal and evaluation requirements.

Two cautions on status, as at October 2026. First, the MoD Integrated Procurement Model, published in February 2024, is the current MoD acquisition framework. We have not confirmed how the MoD now maps CADMID phase names onto the Integrated Procurement Model, so confirm that with your acquisition lead before you label deliverables. Second, MoD Initial Gate and the NISTA Gateway Reviews are separate mechanisms. NISTA (formerly the IPA) took over Gateway Reviews in April 2025. Where a programme sits on the Government Major Projects Portfolio it may also face a Gate 0 or Gate 1 review. Do not treat the two labels as interchangeable.

What controls must deliver at Concept

The cost estimate is a Class 5 range under the AACE classification system. Class 5 is the least defined class, used for concept screening. AACE 18R-97 gives typical ranges of -20% to -50% on the low side and +30% to +100% on the high side. 18R-97 is written for process industries and 56R-08 for building and general construction. 17R-97 is the generic framework. None of them is written for defence equipment, so use the bands as a sense check and set the actual range from the option-level analysis.

The QRA at Concept is option-level. There is no definitive cost to which a P80 can be applied, so the job is to compare options on a like-for-like basis. A bespoke airframe and a military off-the-shelf (MOTS) variant should not carry the same coefficient of variation, and the analysis should show that difference. The range-estimating and parametric methods in AACE 41R-08 and 42R-08 suit this stage better than a full integrated cost and schedule simulation, which needs a schedule logic that Concept does not have.

The risk register at Concept holds strategic risks at option-set level. In SOMA practice that is roughly 20 to 40 risks, each mapped to the options it affects. That figure is a rule of thumb. A register of several hundred line-level risks usually means the team has not abstracted to the level of the decision.

Reference-class comparison checks each option range against the outturn of comparable programmes. The Green Book requires optimism bias and risk to be addressed in the economic appraisal and treats reference-class evidence as an input to that. Agree with the reviewer which evidence you are using before you build the case.

Optimism bias and QRA: avoid double counting

Optimism bias is an adjustment for the known tendency of early estimates to understate cost and duration. A QRA models identified risks and uncertainties. If the QRA already prices a risk and the optimism-bias uplift is then applied in full on top, the same exposure is counted twice. The Green Book approach is to start from the optimism-bias adjustment and reduce it as specific risks are identified and mitigated.

Set out the split in the case. State the base estimate, the risks the QRA prices, the optimism-bias adjustment that remains, and the reason it is not duplicated. A reviewer who can see the three layers separately can test them. A single blended contingency cannot be tested. Do not hide the adjustment inside the input ranges and then present the output as unadjusted.

Worked example: three options

The figures below are hypothetical and use a normal approximation, where P80 is about P50 x (1 + 0.84 x CoV). The approximation is crude for skewed cost distributions, so a real analysis would use fitted distributions in line with AACE 66R-11.

Cost, in £m. Option A, bespoke design: P50 1,200, CoV 35%, P80 about 1,553 (1,200 x 1.294). Option B, MOTS: P50 800, CoV 15%, P80 about 901 (800 x 1.126). Option C, modified MOTS: P50 950, CoV 25%, P80 about 1,150 (950 x 1.21). The spread rises with technical maturity risk: the more the design departs from a fielded product, the wider the range.

Schedule, in months to initial operating capability. Option A: P50 84, CoV 20%, P80 about 98 (84 x 1.168). Option B: P50 60, CoV 10%, P80 about 65 (60 x 1.084). Option C: P50 72, CoV 15%, P80 about 81 (72 x 1.126).

Correlation. Only one option will be built, so the options are not summed. Correlation matters in two places. Within each option, cost and schedule are positively correlated because delay carries cost. Between options, shared drivers such as requirement growth and a common supplier base should be run from the same sampled values, so that the comparison of option differences is not distorted by noise in separate runs.

Reference-class cross-check. Suppose comparable programmes show median outturn of 40% above the Concept P50 for bespoke designs, 10% for MOTS and 25% for modified variants. That gives 1,680 for A (1,200 x 1.40), 880 for B (800 x 1.10) and 1,188 for C (950 x 1.25). B and C are close to their QRA P80 values. A is about £127m above its P80 of 1,553, so the QRA is probably too optimistic for the bespoke option and the team must explain the gap or re-examine the input ranges.

What reviewers look for at Initial Gate

Reviewers are independent of the programme team and read the controls evidence to test whether the cost and time range reflects the uncertainty of the concept, and whether the options have been compared or one has been engineered to look best.

Common red flags are a high-end cost that sits just under the funding envelope, option uncertainties flattened to similar coefficients of variation, an optimism-bias adjustment that cannot be separated from the QRA, a missing or non-comparable reference class, and top risks that do not match the recommended option.

Controls evidence tends to withstand review when the numbers are traceable, the methodology is conventional so that reviewers do not spend time on method choices, and the narrative states where the team is confident, where it is not and what Assessment will resolve.

Failure modes

Over-precision is the first failure mode. The Class 5 range is narrowed because the board wants reassurance. A narrow range at this stage reflects a definition the programme does not have, and the number then becomes an anchor that the later analysis cannot support.

Over-elaboration is the second. A Class 3 style cost breakdown is built before the requirement can support it. Reviewers notice when the breakdown is finer than the requirement.

The third is the missing reference class. An estimate built bottom-up with no comparison to outturn on similar programmes leaves the reviewer asking what this category of programme usually costs, and the team has no answer.

How SOMA approaches this

On a Concept-stage review we check four things in order: whether the range matches the class, whether option uncertainty is differentiated by maturity, whether optimism bias and priced risk are separated, and whether the reference class is comparable.