Adam O'NeillLast updated 9 min readPart of Defence & government project controls

What is CADMID Assessment phase?

Assessment is the second phase of the MOD acquisition lifecycle (Concept, Assessment, Demonstration, Manufacture, In-service, Disposal). Options are examined in detail, a preferred solution is selected, and the Full Business Case is built. The phase ends at Main Gate, where the Investment Approvals Committee decides whether to commit to Demonstration.

Assessment-phase controls deliverables and the question a reviewer asks of each.

Point in AssessmentControls deliverableReferenceReviewer test
EarlyOption comparison frameworkHM Treasury Green Book, Five Case ModelAre options assessed like for like?
MidEstimate per remaining option, at the level of definition availableAACE 17R-97 Cost Estimate Classification System (generic); 18R-97 or 56R-08 where the sector fitsIs each estimate supported by quantified inputs at the right level of definition?
MidIntegrated cost and schedule risk analysis per optionAACE 57R-09; 41R-08; 66R-11Are cost and schedule sampled together, with justified correlation?
MidBaseline programme draft for the preferred optionDCMA 14-point schedule check (widely used)Is the critical path genuine and the logic sound?
LateOptimism bias and risk adjustmentHM Treasury Green BookIs the adjustment visible, reasoned and free of double counting?
EndFull Business Case controls evidence packFive Case Model; JSP 507Is the case affordable, achievable, deliverable and assured?

Where Assessment fits in CADMID

CADMID has six phases: Concept, Assessment, Demonstration, Manufacture, In-service and Disposal. MOD investment approvals sit at two points. Initial Gate closes Concept and approves the Strategic Outline Case or Outline Business Case, depending on the project. Main Gate closes Assessment and approves the Full Business Case and entry to Demonstration. Both go to the Investment Approvals Committee, and JSP 507 sets the investment appraisal and evaluation rules.

Assessment therefore starts from an approved outline case and ends on a full one. What carries forward from Concept is the option set, the Class 5-level cost ranges, the strategic risk register and the outline programme. What gets re-baselined is nearly everything else: estimates are rebuilt on design definition, the risk register is rewritten as a working document, and the programme gains real logic.

The Integrated Procurement Model (February 2024) is the current MOD procurement framework. CADMID phase and gate names remain in wide use in project controls practice. Confirm the phase and gate terms in your own approvals paperwork before you build a controls plan around them.

CADMID gates and NISTA Gateway Reviews

NISTA (the National Infrastructure and Service Transformation Authority) replaced the Infrastructure and Projects Authority (IPA) in April 2025. Gateway Reviews (Gate 0 to 5) continue. Gate 2 tests delivery strategy and Gate 3 tests the investment decision.

MOD approvals and Gateway Reviews are separate processes. Main Gate is an approval decision. A Gateway Review is independent assurance that feeds it. How Gate 2 and Gate 3 line up with Initial Gate and Main Gate varies by project, so agree the mapping with the review team at the start of Assessment and write it into the assurance plan.

What controls must deliver at Assessment

Estimate. Build each option's estimate on a defined cost breakdown structure, with every major element traced to a quantified basis: engineering definition, supplier engagement or reference-class data. AACE classes are not MOD's native estimating convention, but they are a reasonable common language for definition and accuracy. Under AACE 18R-97 a Class 3 estimate typically runs from about -10% to -20% at the low end to +10% to +30% at the high end. Class 4 sits between Concept and Class 3, and an option that is still Class 4 at Main Gate needs that stated openly.

Risk analysis. Run cost and schedule together against one risk register, with correlation where risks hit both. Tools such as Safran Risk, Oracle Primavera Risk Analysis, @RISK and Deltek Acumen Risk can all do this. The method matters more than the tool: AACE 57R-09 covers integrated analysis with risk drivers, 41R-08 range estimating and 66R-11 distribution selection. The model file should be auditable.

Percentile. State once, in writing, which percentile is the funding basis and which is held as contingency. The Green Book does not prescribe P80. It requires optimism-bias and risk adjustment, and the confidence level for funding and contingency is a Defence and sponsor decision. Agree it with the sponsor and cost assurance team before the first model run, then report P50 and the chosen contingency percentile against the deterministic base.

Programme. The baseline draft covers Demonstration and Manufacture in enough detail for review. The critical path is identifiable and the logic is genuine, not a string of FS-0 links hiding a missing path. Run the DCMA 14-point check before the programme goes into the case.

Risk register. Probabilities are numeric and impacts are three-point, not RAG bands. Each risk maps to schedule activities and cost lines, and the top risks reconcile to the QRA outputs.

Optimism bias and risk adjustment

The Green Book treats optimism bias as a top-down uplift taken from reference-class evidence, then reduced as specific risks are identified, quantified and mitigated. A bottom-up QRA already prices those specific risks. Add a full uplift on top and the same exposure is counted twice.

Our view is that what matters is whether the adjustment is visible and reasoned, wherever it sits. Show the bottom-up contingency, the optimism-bias element and the reduction argued for each, as separate lines. A reviewer can then see what was removed and why. A late uplift added to satisfy the Green Book with no link to the inputs is the version that gets challenged. Cite the Green Book section on optimism bias and its supplementary guidance, and say which reference class you used.

What Main Gate reviewers test

Reviewers are not asking whether the team can produce a number. They are asking whether the number survives questioning. Typical lines are these.

Delivery strategy: is the PMB achievable given technical maturity, is the supply chain capable, and will the earned value management system (EVMS) proposed for Demonstration produce measured data rather than earned value reconciled back from spend? Would the schedule survive realistic contractor delay, and would the funding case still hold if supplier assumptions tighten?

Investment confidence: is the contingency defensible against the risks identified, does the cost breakdown reconcile to the technical scope, and is the risk transfer to industry real? A transfer on paper that the MOD ends up bearing anyway is a recurring finding. Where contract strategy touches the Procurement Act 2023 (in force 24 February 2025), the commercial team should confirm the route before risk allocation is priced.

The recurring failure modes

Distributions too tame for the maturity. Three-point ranges are narrow, correlation is absent or token, the opportunity side is empty, and the contingency percentile sits close to the deterministic estimate. Inputs look engineered to a target rather than calibrated. Challenge each range against evidence, such as outturn data on similar equipment.

Optimism bias bolted on late. A P80 is produced, an uplift is added at the end, and the inputs are not revisited. Reviewers remove the uplift, look at the underlying figure and ask whether it still supports the case.

A schedule that cannot survive contractor reality. The baseline is built top-down to a desired Main Gate date, with logic written to fit it. The DCMA check exposes this quickly: high constraint counts, odd float distributions and missing successors on tasks that should not be terminal.

A register that does not tie to the QRA. The register has one top ten and the model has another. The reviewer asks which five risks, in combination, would breach the contingency percentile, and the two documents give different answers.

Worked example: reconciling the register to the QRA

The figures below are illustrative. A deterministic base of £440m, a P50 of £480m and a P80 of £531m give contingency of £40m to P50 (480 - 440) and £91m to P80 (531 - 440), which is 20.7% of base (91 / 440). The gap from P50 to P80 is £51m (531 - 480).

The register's top five by expected value are supplier design maturity (£14m), software integration (£11m), trials slippage (£9m), obsolescence (£4m) and infrastructure readiness (£3m). The QRA sensitivity ranking puts software integration first, then supplier design maturity, trials slippage, exchange rate and infrastructure readiness.

Four risks agree on membership if not on order. The two that do not are the finding. Obsolescence is in the register but not driving the model, so check whether its range was entered correctly. Exchange rate drives the model but is outside the register's top ten, so someone has been managing a major exposure as a commercial assumption. Fix both, then re-run. Order differences alone are normal, because expected value and sensitivity measure different things.

Pre-Main Gate controls checklist

Estimate: each option on a defined cost breakdown structure, basis of estimate for every major element, AACE class stated per element with the accuracy range, and escalation and exchange rate assumptions listed.

Risk analysis: percentile policy agreed and written down, correlation justified, opportunities included, optimism-bias treatment shown separately, model file and input log available for audit.

Register: numeric probabilities, three-point impacts, owners, mapping to activities and cost lines, top risks reconcile to model sensitivity.

Programme, DCMA 14-point thresholds: missing logic 5% or less, leads 0%, lags 5% or less, finish-to-start relationships 90% or more, hard constraints 5% or less, high float over 44 working days 5% or less, negative float 0, high duration over 44 working days 5% or less, invalid dates 0, all tasks with duration resourced, missed tasks 5% or less, critical path test passed, Critical Path Length Index 0.95 or more, Baseline Execution Index 0.95 or more. Note that the DCMA check is a US Department of Defense origin test used widely in UK practice. It is not a MOD mandate.

Narrative: the Full Business Case reads as one document, with cost, risk, schedule, supply chain and assurance sections built on the same stated assumptions, so a reviewer can sensitivity-test them.

How SOMA approaches Assessment-stage risk analysis

On a quantitative risk analysis the test we apply is whether every contingency pound can be traced to a risk, a range and an evidence source, and whether the register and model name the same top risks. Our evidenced QRA work is on National Highways major projects and on an industrial capital programme, with independent risk assurance in the nuclear sector. We have not delivered a MOD Main Gate submission, so on a defence case we would work alongside the programme's own cost assurance team.