Adam O'NeillLast updated 10 min readPart of Earned value (EVM) and cost contingency

What is Budget at Completion (BAC)?

Budget at Completion (BAC) is the sum of all budgets for the work in the performance measurement baseline: control-account budgets, summary-level planning packages and undistributed budget. It excludes management reserve. It is the terminal value of the cumulative planned value curve and the numerator in EAC = BAC ÷ CPI.

Core EVM forecast measures. Worked figures are in the example below.

MetricFormulaWhat it tells youNotes
BACΣ control-account budgets + planning packages + UBTotal authorised budget for the scopeSet at baseline; changed only by controlled change
EV% complete × work-package budgetBudgeted value of work doneEarned under the EVMS progress rules
EACBAC ÷ CPI (typical); AC + (BAC − EV) (atypical); BAC ÷ (CPI × SPI)Forecast total costState the assumption; rerun each period
ETCEAC − ACForecast cost of remaining workCross-check with bottom-up estimate
VACBAC − EACForecast under or overspendNegative means overspend
TCPI(BAC − EV) ÷ (BAC − AC)CPI needed on remaining work to land at BACSOMA judgement: BAC at risk when TCPI exceeds cumulative CPI by more than 0.10

What BAC is

Budget at Completion is the total budget authorised for the agreed scope. It is built bottom-up from the budgets of the control accounts in the Work Breakdown Structure, together with summary-level planning packages and any undistributed budget, and then frozen as part of the performance measurement baseline (PMB). BAC is the terminal value of the cumulative planned value (PV) curve: read the curve at the planned finish date and you have BAC. It is a sum of money, not an area under the curve.

BAC feeds the forecast set directly. Estimate at Completion (EAC) is BAC divided by the Cost Performance Index (CPI), so BAC is the numerator and CPI the denominator. Variance at Completion (VAC) is BAC minus EAC. The To-Complete Performance Index (TCPI) uses BAC in both its numerator and its denominator. If BAC drifts without a recorded change, every one of these drifts with it.

BAC is not the contract price, which usually sits above it because it carries margin and any risk the contractor prices outside the baseline. It is not the funded position, because funding may be released in tranches. It is not management reserve, which is held outside the PMB. The relevant standards are ANSI/EIA-748 (current revision), ISO 21508:2018 Earned value management in project and programme management, and the APM Earned Value Management Handbook.

The formula, and what sits inside and outside it

BAC = Σ control-account budgets + summary-level planning package budgets + undistributed budget. Undistributed budget (UB) is authorised budget not yet assigned to a control account. It is part of the PMB and so part of BAC, but nothing is earned against it until it is distributed, so a large UB late in planning means the baseline is incomplete.

Three different pots get called contingency or reserve, and mixing them is the commonest source of confusion. Contractor contingency is a risk allowance for identified risks that the contractor has budgeted inside the PMB, distributed to control accounts or held at project level within the baseline. It is inside BAC. Management reserve (MR) is held by the contractor outside the PMB for unknown events. It is not in BAC, and the Contract Budget Base (CBB) is PMB plus MR. Client reserve is the client's own risk allowance, held in its approved budget outside the contract price. It is not in the contractor's BAC, MR or price.

The viewpoint therefore matters. A contractor's BAC and a client's cost plan for the same work are different numbers, and a statement such as BAC includes contingency only makes sense once you say whose BAC it is. The Green Book (2026 edition, optimism bias and risk adjustment) applies to the client's appraisal, not to the contractor's PMB.

Worked example

The viewpoint here is the contractor's. A 20-week electrical commissioning project has four control accounts. A, site setup and temporary supplies, has a budget of £180,000. B, primary equipment install, £420,000. C, secondary distribution and testing, £290,000. D, handover, commissioning and demobilisation, £110,000. There is no UB or planning package. BAC = 180,000 + 420,000 + 290,000 + 110,000 = £1,000,000.

The contract price is £1,150,000. We assume the £150,000 above BAC is a £100,000 management reserve held by the contractor outside the PMB (so CBB = £1,100,000) and £50,000 of margin. The client holds its own reserve separately and it does not appear in these numbers.

Six weeks in, the project has PV = £350,000 (35.0% of BAC), EV = £315,000 (31.5%) and AC = £360,000 (36.0%). CPI = EV ÷ AC = 315,000 ÷ 360,000 = 0.875. SPI = EV ÷ PV = 315,000 ÷ 350,000 = 0.900. The project is behind plan and spending more than it has earned.

TCPI to reach BAC = (BAC − EV) ÷ (BAC − AC) = 685,000 ÷ 640,000 = 1.07. The remaining work must be delivered at a CPI of 1.07 against 0.875 achieved so far. As SOMA judgement, not a published standard, we treat BAC as unachievable when TCPI exceeds the current cumulative CPI by more than 0.10 and no recovery action has been identified. The gap here is 0.195, so the test is met. A TCPI above 1.10 is a separate, commonly quoted rule of thumb, and it does not apply here.

Choosing the EAC

EAC = BAC ÷ CPI is one forecast, built on the assumption that cost performance to date continues. There are two other standard variants, and the assumption behind each should be stated with the number.

Typical variance, EAC = BAC ÷ CPI = 1,000,000 ÷ 0.875 = £1,142,857 (rounded to the pound). VAC = −£142,857. Estimate to Complete (ETC) = EAC − AC = 1,142,857 − 360,000 = £782,857. Check: (BAC − EV) ÷ CPI = 685,000 ÷ 0.875 = £782,857. Use it when the overrun looks systemic.

Atypical variance, EAC = AC + (BAC − EV) = 360,000 + 685,000 = £1,045,000. VAC = −£45,000. ETC = £685,000. Use it only when the overrun came from a one-off event that has been resolved and the remaining work will earn at plan.

Cost and schedule combined, EAC = BAC ÷ (CPI × SPI) = 1,000,000 ÷ (0.875 × 0.900) = 1,000,000 ÷ 0.7875 = £1,269,841. VAC = −£269,841. ETC = £909,841. Use it when schedule slip is itself driving cost, for example through extended preliminaries.

The spread is £1,045,000 to £1,269,841, so the early forecast is a range. Cumulative CPI can still move materially at 31.5% complete, and the forecast should be rerun every period. A bottom-up ETC from the remaining work packages, checked against the CPI-based figure, is the better test than any single formula.

Against the £1,150,000 price, the CPI-based EAC leaves £7,143 of the £150,000 headroom. The forecast overspend of £142,857 is £42,857 more than the £100,000 management reserve, so even a full draw on MR would not cover it and the margin would be consumed. On the combined variant the project is loss-making by £119,841.

The response options follow the change rules below. They are a recovery plan to bring CPI up, a scope reduction agreed with the client, or a formal change with a documented cause if the client has instructed extra work. MR is not a general overrun fund. A draw is justified only for an identified risk event that has materialised, and spending it to absorb a CPI-driven overrun is the rolling re-plan described next. For a client on a fixed price the overrun falls on the contractor. On NEC4 Option C or D the client shares it through the target cost pain/gain mechanism, so the client reserve is exposed.

When BAC changes, and when it should not

BAC changes only through controlled change. The two legitimate triggers are an approved scope change that adds or removes work from the PMB, and a transfer of MR into the PMB to fund a materialised risk that has been turned into scope. Each should produce a baseline revision number, a documented Baseline Change Request and a re-published PMB.

The illegitimate version is the rolling re-plan, also called a rubber baseline. Work packages are quietly re-budgeted to absorb variances, the PV curve is reshaped to hide slip, and BAC stays the same on paper while the baseline moves in step with the actuals. CPI and SPI then look stable when they are not. The control is a cumulative change log on the cost report that reconciles original BAC, approved changes and MR transfers to the current BAC.

Four housekeeping failures that invalidate BAC

First, contingency absorbing overruns. Contractor contingency inside the PMB is legitimate when it is held against named risks. When it is released into control accounts to cover cost growth with no scope change, CPI and EAC both look better than the work justifies. They move in the same direction, so the report improves while performance does not. The test is to reconcile original BAC, contingency distributed to date, approved scope changes and MR drawn to the current BAC and CBB, and to ask what each transfer was for.

Second, undistributed budget that stays undistributed. UB is a placeholder for authorised work not yet assigned to a control account. As an illustration, UB still present halfway through the programme means that part of the PV curve is a guess, and the earned value for that work cannot be measured.

Third, rubber work packages. A package whose budget is repeatedly moved to balance variances has stopped being a unit of management. Our test: a transfer within a control account is at the control account manager's discretion and logged, while a transfer between control accounts goes through formal change control.

Fourth, contracted scope left outside BAC. Long-lead procurement is the usual case: items ordered against the contract but parked outside the PMB. EV is then earned against a BAC that omits real work, and CPI looks better than it is. BAC should reconcile to the contracted scope, with the bridge from BAC to price explained line by line.

BAC and quantitative risk

On a QCRA we compare BAC and the contractor contingency in it with the cost risk model. The test is whether BAC plus contingency reaches the chosen confidence level (for example P80), and where MR and any client reserve are needed to cover the gap. A BAC with no stated contingency is a baseline that assumes no risk occurs.

Putting EVM and cost contingency to work?

SOMA helps controls leads run earned value the way the contract allows it: disciplined earning rules, CPI and SPI you can defend, and cost and schedule contingency held in the right place. We work alongside your team rather than handing over a deck.