Adam O'NeillLast updated 10 min readPart of NEC4 programme controls

What is NEC4 clause 32?

Clause 32 of the NEC4 Engineering and Construction Contract governs revisions to the Accepted Programme. The Contractor submits a revised programme at intervals no longer than the Contract Data interval, when the Project Manager instructs, and when the Contractor chooses. The Project Manager must accept it or give a stated reason for non-acceptance within two weeks.

Five recurring failures on NEC4 ECC programme management and their contract consequences

FailureWhat follows under the contractPractical fix
Contractor submits revisions late or thinRisk that the latest programme is not accepted for a clause 31.3 reason, which can leave the Project Manager assessing compensation events on the Project Manager's own view of the programme (clause 64.2)Submit at the reporting date with every 32.1 item present
Project Manager does not reply within two weeksContractor may notify the failure; if there is still no reply one further week later, the revision is treated as accepted. Failure to reply is also a compensation event (60.1(6))Diarise the two-week date on receipt and reply in substance
Project Manager refuses acceptance for a reason outside clause 31.3The refusal is open to challenge and the Accepted Programme stays out of date in the meantimeContractor resubmits addressing the stated reason; escalate under W1 or W2 if it does not move
Implemented compensation events are not reflectedThe next assessment under clause 63 starts from a programme that no longer matches the worksShow each implemented event in the next revision, or use the Contractor's own-choice limb sooner
Contractor never sends the notification after a missed replyThe one-week deemed-acceptance period does not startSend the notification promptly and keep proof of delivery

Where clause 32 sits

This guide covers NEC4 ECC (2017, amended January 2019 and October 2020). Check any later amendment and your Z clauses before relying on it. It is general guidance, not legal advice. Where we describe a mechanism without quoting the clause, read the clause itself before you put it in a notice.

The Accepted Programme is the programme the Project Manager has accepted, or that is treated as accepted, under clause 31. Clause 32 keeps it current. Clause 63 then assesses the time effect of a compensation event against the Accepted Programme current at the dividing date. A stale Accepted Programme therefore sits underneath every time assessment on the contract.

When a revision is due

Clause 32.2 gives three occasions on which the Contractor submits a revised programme: at intervals no longer than the interval stated in the Contract Data; within the period for reply after the Project Manager instructs it to; and whenever the Contractor chooses to.

The Contract Data interval is a maximum gap between submissions. It is not a minimum, and nothing stops the Contractor submitting more often. If the interval is left blank, the first limb has nothing to work with, but the instruction and own-choice limbs still operate, and a Contractor that fails to submit a programme the contract requires carries the clause 64.2 consequence described below.

There is no limb of 32.2 that says a revision is due when a compensation event has occurred. The compensation event route runs through other clauses. A quotation under clause 62.2 includes any alterations to the Accepted Programme. Once the event is implemented, the next revision must show its effect. A Contractor that wants a large event reflected before the next interval date uses the own-choice limb. A Project Manager who wants it sooner instructs a revision.

Acceleration under clause 36 is a second route that does not depend on a compensation event. The Project Manager can instruct the Contractor to submit a quotation for acceleration to complete before the Completion Date. The quotation is submitted with a revised programme showing the acceleration. If the Project Manager accepts it, the Prices, the Completion Date and any Key Dates change and that revised programme is accepted with it.

Set the interval to match the reporting cycle, so that the data date of each revision lines up with the period the cost and progress reports cover.

What each revision must show

A revision carries the content required of the first programme under clause 31.2, including float and any time risk allowance, and adds what clause 32.1 requires. In plain words, that is: actual progress on each operation and its effect on the timing of the remaining work; the effects of implemented compensation events; the effects of notified early warning matters; how the Contractor plans to deal with any delays and to correct notified Defects; and any other changes the Contractor proposes.

A practical submission checklist follows from that.

1. The data date is the reporting date, with actual starts, actual finishes and remaining durations for every operation in progress.

2. The remaining network recalculates from the data date, without manual date overrides.

3. Each implemented compensation event is identifiable, with its effect on planned Completion visible.

4. Each notified early warning matter is either reflected or recorded as still under assessment. An unquantified matter should still be visible.

5. Delays are explained, with the recovery or mitigation plan, and notified Defects have a correction plan.

6. Every change from the previous revision (logic, durations, sequence, methods, resources) is listed with its reason.

7. Planned Completion, the Completion Date, Key Dates, float and time risk allowance are stated, and any change to the time risk allowance is explained.

The acceptance loop and deemed acceptance

Under clause 31.3 the Project Manager replies within two weeks, either accepting the revision or giving reasons for non-acceptance. The reasons available are, in summary: the Contractor's plans are not practicable; the programme does not show the information the contract requires; it does not represent the Contractor's plans realistically; or it does not comply with the Scope. A later completion date is not a reason. Nor is unease about a change of method. The reason given should be specific enough for the Contractor to correct it.

The two weeks is fixed by clause 31.3. The period for reply stated in the Contract Data is a different period, and it is the one that governs how quickly the Contractor must respond to a Project Manager's instruction to revise.

If the Project Manager does not reply within two weeks, the Contractor may notify the Project Manager of the failure. If the Project Manager has still not replied one further week after that notification, the revision is treated as accepted and becomes the Accepted Programme. Project Manager silence is therefore not a safe position for the Client: a programme nobody has examined can become the contractual baseline. For the Contractor, the clock only runs once the notification has been given, so it should be sent promptly and its delivery recorded.

A failure to reply within the period is also a compensation event under clause 60.1(6). The Contractor notifies it under clause 61.3, within eight weeks of becoming aware, and it is assessed on its actual effect, which is often small when the programme is later accepted.

If the Contractor disagrees with a stated reason, the fastest step is to resubmit addressing it. If the disagreement is on a matter of contract rather than content, the dispute procedure applies: Option W1 or W2, as varied by any Z clauses.

A reply that works for either outcome is short. Acceptance: 'The revised programme submitted on [date], data date [date], is accepted under clause 31.3.' Non-acceptance: 'The revised programme submitted on [date] is not accepted. Reason: it does not show [specific item] required by clause 32.1. Please resubmit showing [what is needed].'

Why currency matters at clause 63 and clause 64.2

Clause 63 measures the delay a compensation event causes as the length of time by which planned Completion becomes later than planned Completion on the Accepted Programme, using the programme current at the dividing date. Whether the affected activity is critical, and how much float it has, are both read from that programme.

Clause 64.2 sets out what happens when the programme is not there to use. In summary, if there is no Accepted Programme, or the Contractor has not submitted a programme or revision the contract requires, or the Project Manager has not accepted the Contractor's latest programme for one of the clause 31.3 reasons, the Project Manager assesses the event using the Project Manager's own assessment of the programme for the remaining work. That is a Contractor-side consequence. Distinguish it from a programme that is merely old but still in force: an old Accepted Programme is still the reference, but a poor one. The contract also allows part of the payment to be retained until a first programme showing the required information has been submitted.

A worked example shows the effect. Accepted Programme Revision 4 shows planned Completion on 12 March 2027 and the Completion Date as 26 March 2027. A compensation event delays an activity by three weeks. On Revision 4 the activity is critical, so planned Completion moves to 2 April 2027 and the Completion Date moves three weeks to 16 April 2027.

Revision 5, with progress to date, shows the critical path has moved and the same activity now has two weeks of total float. Assessed against Revision 5, the three-week delay moves planned Completion by one week, to 19 March 2027, and the Completion Date by one week to 2 April 2027. The difference between the stale and the current programme is two weeks of Completion Date, which here favours the Contractor. Had the critical path moved the other way, it would have favoured the Client. Either way the answer depends on which programme is the Accepted Programme at the dividing date, which is why revision and acceptance discipline matters to both parties.

The QSRA angle

A schedule risk analysis models the remaining work from a data date on a logic network. If the Accepted Programme behind it is out of date, the model starts from the wrong remaining durations, the wrong logic and the wrong critical path. The P50 and P80 completion dates it produces describe a plan nobody is executing, and the risk drivers mapped to activities may sit on work that has already finished.

The same programme carries the time risk allowance the Contractor shows under clause 31.2. Where a QSRA exists, the two should be consistent, so that risk is not counted once as an allowance in the programme and again in the model. NEC4 does not require a QSRA. Where one is used, it needs a current Accepted Programme.

On a QSRA we first ask which programme the Client treats as current, when it was last accepted and what has been implemented since. If those answers are unclear, the first output is a list of corrections to the programme, not a risk result.

Running an NEC4 programme?

NEC4 asks a lot of the controls function: an Accepted Programme that is current, an Early Warning Register that is used, and evidence behind every compensation event. SOMA helps client teams turn the contract into day-to-day practice.