At a glance

Client
Northumbrian Water (via Gardiner & Theobald)
Sector
Water & utilities
Services
  • PMO risk leadership
  • Risk process transformation
  • Risk register governance
  • Opportunity Management training
  • Contingency alignment

The brief

Northumbrian Water’s PMO was running a 400-project capital portfolio. Risk management existed, but identification discipline, register quality and contingency alignment were uneven — and the sheer volume of governance activity was consuming operational capacity faster than it could be created.

SOMA, engaged through Gardiner & Theobald, was brought in to lead risk transformation inside the PMO: rebuild the risk process, upskill the team, and realign contingency planning with the actual risk exposure sitting on the portfolio.

Our role

SOMA acted as PMO Risk Lead, reporting to the Risk Management Director and leading a team of 5+ risk professionals across the portfolio. The scope covered:

  • Process refinement — working with the Risk Management Director to redesign identification, quantification and reporting processes, removing duplicated effort and embedding proactive risk identification in the PMO cadence.
  • Register governance — maintained comprehensive risk registers across the 400-project portfolio, with consistent metalanguage, clear ownership, and alignment between qualitative scoring and quantitative exposure.
  • Tailored workshops — facilitated risk workshops sized to the project rather than the template, with different depth for capital, regulatory, and operational workstreams.
  • Opportunity Management training — a formal training programme designed to shift the culture from threat-only to threat-plus-opportunity, and build identification capability across the PMO.
  • Senior reporting — progress reporting to senior leadership, with a clear line from individual-project risk exposure through to portfolio-level contingency position.

What changed

The risk process was simplified and duplicated effort removed from the PMO’s risk management activity. Staff risk-identification capability was built through the Opportunity Management training.

Behind the numbers, contingency planning was realigned with the actual risk exposure sitting across the 400-project portfolio — reducing the gap between provision and reality and lowering the probability of financial overrun.

Outcomes

  • Duplicated effort removed from the PMO’s risk management processes.
  • Staff risk-identification capability built through Opportunity Management training.
  • Contingency planning aligned with realistic risk exposure — reducing financial overrun exposure.
  • Consistent risk register discipline across the 400-project portfolio.
  • Team of 5+ risk professionals led and developed through the transformation.

The result

A programme of process discipline, proper training, and steady leadership — the unglamorous work that actually moves risk maturity. SOMA through and through.