What a DCMA 14 result tells you
The DCMA 14-point assessment came out of the US Department of Defense as a quick, repeatable screen for contractor schedules. It is widely used in UK practice as a first-pass quality check on infrastructure, energy and nuclear programmes. It is not mandated by National Highways, Network Rail or HS2, so the pass marks have no standing unless your own contract or scheduling specification adopts them.
The result is fourteen pass or breach flags. It says nothing about whether the sequencing is sensible, the durations are realistic or the plan reflects how the work will be built. A schedule can pass all fourteen and still mislead. A schedule can breach several for good reasons. A reviewer who reports every breach as non-compliance is producing a list, and the skill lies in deciding which items on the list matter.
This guide covers interpretation and review writing. The full metric definitions and thresholds are in the companion guide on the DCMA 14-point assessment in UK practice. State the tool, version and settings behind any result you quote. Tools differ in which task types they exclude (completed tasks, milestones, level-of-effort) and in the calendar used for the 44-day tests, so the same schedule can return different percentages.
The breaches that are most often acceptable
Lags, Hard Constraints and High Duration produce the breaches that most often turn out to be acceptable once someone asks what is behind them. Treating a breach as a finding without asking that question is the quickest way to lose the Contractor's attention for the rest of the review.
Lags. The test counts relationships carrying a positive lag, against a pass mark of 5% of relationships. Accept a lag that stands for a physical or contractual wait which no change of logic removes: concrete curing before formwork is struck, grout or coupler cure before a connection is loaded, drying time between paint coats, or a notice period before access or handover. Query a lag when it has a duration with no stated basis, when it sits on the critical path and absorbs time that should be shown as float, when it is combined with start-to-start or finish-to-finish links, or when it stands in for work that someone has to do, such as an inspection. If a wait needs its own owner, resource or progress measure, it should be an activity rather than a lag.
Hard Constraints. The test counts Must Start On, Must Finish On, Start No Later Than and Finish No Later Than constraints, against a pass mark of 5% of incomplete tasks. Start No Earlier Than and Finish No Earlier Than are soft constraints and are not counted. A planning condition barring works before a given date is a Start No Earlier Than, so it is both the right constraint and outside this test. Accept a hard constraint when the Contractor can name the clause, permit or third-party date behind it. Query any that sit inside a work package with no stated basis.
Contractual completion dates need care. A mandatory date on a completion milestone pins its float at zero, so negative float can never appear there. Where the tool allows it, carry the contractual date as a deadline, which leaves the logic to calculate the date and shows any shortfall as negative float. A mandatory date on a milestone should still be queried even when the date is contractual.
High Duration. The test counts incomplete tasks longer than 44 working days, against a pass mark of 5%. Accept long durations for procurement, fabrication and regulatory approvals, provided there are interim milestones or a tracker that shows progress. Query site work of more than 44 working days that has no way of measuring percent complete, because it will report nothing until it is late.
One rule covers all three. For each breach, ask what the item is, what physical or contractual fact justifies it, and whether it changes float or the finish date. Record the answer in the report.
The breaches that usually point to a real problem
Four tests rarely fail for a good reason: Logic, Negative Float, Invalid Dates and the Critical Path Test. Pursue any breach until you understand it.
Logic. The test counts incomplete tasks missing a predecessor or a successor, against a pass mark of 5%. The project start and finish milestones are the usual legitimate exceptions. Anything else needs an answer to three questions: what is this activity, why is it not connected, and was it disconnected to avoid a negative float calculation.
Negative Float. The pass mark is zero. A critical path with negative float says, in arithmetic, that the current plan does not deliver the target date. The test cannot tell you why, how large the miss is in cost terms or whether a recovery plan exists. The Contractor must either show that the float is a modelling artefact, such as a wrongly set constraint, or present a credible recovery. Negative float left out of a review report is a missed finding.
Invalid Dates. The pass mark is zero. The test finds actual dates after the status date and forecast dates before it. Every float and critical path calculation depends on the status date, so a schedule that fails here has not been properly updated and its outputs are unreliable until it is corrected.
Critical Path Test. This is a method rather than a count. Add a large artificial delay to a critical task on a copy of the schedule, recalculate, and check that the project finish moves by the same amount. If it does, the logic carries the delay to the end. If the finish does not move, there is a break in the logic between that task and the finish. A true logic loop stops the calculation altogether. Delete the test copy afterwards.
Two further tests are indices rather than counts. The CPLI looks forward and the BEI looks back. The Critical Path Length Index is (critical path length + total float) ÷ critical path length, with a pass mark of 0.95. The Baseline Execution Index is tasks completed ÷ tasks baselined to finish by the status date, also with a pass mark of 0.95. Both treat every task or day equally. The worked example below shows a CPLI passing while a milestone is 12 working days late.
Missed Tasks needs a loaded baseline. It counts tasks baselined to finish by the status date that did not finish by their baseline finish, as a percentage of tasks baselined to finish by then, against a pass mark of 5%. Without a baseline it cannot be run, and it is a different test from Invalid Dates. Resources has no percentage pass mark: the test is that every incomplete task with a duration above zero carries a resource or cost. Where the schedule is not loaded, or the Contractor holds resources in another tool, report coverage as informational and take any target from the contract scheduling specification.
A worked example
The table below reads one result. The schedule has 1,600 incomplete tasks, 3,200 relationships and 400 tasks baselined to finish by the status date. The critical path is 300 working days long. Verdicts are Pass, Explain (a breach that is probably acceptable, so ask for the basis) and Act (a breach the Contractor must address).
Two readings follow from the table. First, Missed Tasks and the BEI are two views of the same slippage, 52 of 400 tasks, so the finding is one problem and is reported once. Second, the CPLI passes at (300 - 12) ÷ 300 = 0.96 while the commissioning milestone carries 12 working days of negative float. A pass on the CPLI does not clear the negative float finding.
Summary for this example: the schedule meets six of the fourteen tests and one is informational. Five Act verdicts cover four findings that need Contractor action: 12 working days of negative float on the commissioning milestone, three forecast dates before the status date, 13.0% of baselined tasks missed with a BEI of 0.87, and 32 hard constraints with no stated basis. The lag and high-float breaches look explainable and are covered by two questions.
Writing the review
A screenshot of the dashboard adds nothing, because anyone with the tool can produce it. The value is interpretation. Open with a three-sentence summary of your overall assessment, as in the example above, so every reader knows at once whether there is a problem and where.
Then cover the breaches that matter, using the schedule data: where the negative float sits, which activities it touches, what it implies for the completion date and what the Contractor has said about it. Then cover the breaches that are acceptable. Most reports leave this section out, and its absence is why Contractors treat reviews as box-ticking. Saying that the lags are curing times and the constraints sit where the Scope puts them shows that you read the schedule.
Rank the actions. A critical path failure or negative float on a key milestone needs a response before the next reporting period. A long procurement activity running to plan needs, at most, a line of observation.
Where the data cannot settle a question, ask for a specific answer. For example: please give the contractual or technical basis for the Finish No Later Than constraint on activity 1047, with the Scope or Contract Data reference. If there is none, please confirm it can be removed and the schedule recalculated. A specific question gets a specific answer. A general request to explain the approach to constraints gets deflection.
On an NEC4 ECC contract the Project Manager has two weeks to reply to a submitted programme under clause 31.3, and the Contractor submits revised programmes under clause 32. A review that supports the Project Manager's reply needs findings specific enough to be used inside that period.
The conversation with the Contractor
Ask before you assert. 'Can you walk me through why this constraint is here' invites an explanation, and you may learn that it is justified. 'This constraint is non-compliant' invites a defence, and if you are wrong you have spent credibility you need for the findings that matter. The same applies to logic: 'activity 1047 has no successor, so how does it connect to the commissioning sequence' either surfaces a sequencing reason or exposes the gap.
For genuine findings, be direct and neutral. 'The schedule is calculating negative float of 12 working days on the commissioning milestone. We need the Contractor's position on this before we can accept the submission.' That sentence states what the data shows and what follows from it.
Say what you are not raising. 'The lags in the concrete sequence look appropriate and we are not raising them' tells the Contractor that the review separates real problems from threshold noise. Contractors who expect every breach to be flagged tend to manage the metrics instead of improving the schedule.
Using the result as a gate before a QSRA
A QSRA simulates the schedule as built, so its structural faults carry into the outputs. A task with no successor cannot pass risk-driven delay to anything, which understates its criticality and sensitivity. A hard constraint caps simulated dates and compresses the distribution against the constraint. Invalid dates and an unreliable status date undermine the basis of the whole run. Negative float means the deterministic plan already misses the target, which changes how the P-values are read.
The test we apply on a QSRA is to run the checks before building the model and not to simulate until the logic, constraint, negative float, invalid date and critical path findings are cleared or documented as accepted. Lags and high float are checked for their effect on the simulation, not for compliance.